top of page

CASE STUDY - 3

Revitalizing Infrastructure: A Case Study of Delhi Metro Rail Corporation's Tank Cleaning Project

​

Introduction:

 

​

The Delhi Metro Rail Corporation (DMRC) faced a critical challenge when the Delhi Fire Services raised concerns about the deteriorating condition of firefighting tanks spread across several stations in Delhi. This case study delves into the collaborative efforts between DMRC and our company, detailing the complexities of the tank cleaning project undertaken to restore essential infrastructure.

Background

 

Constructed two decades ago, the fire fighting tanks, numbering a minimum of 200, had not undergone any cleaning since their inception. The lack of maintenance led to the accumulation of mud, residues, and the potential formation of poisonous gasses. Urgent action was necessitated following a complaint, prompting DMRC to issue tenders and award us the order to execute the cleaning project.

Challenges:

​

The primary challenges stemmed from the neglect of tank cleaning over a  long period of time. Accumulated mud and residues posed a risk to both the tanks' structural integrity and the safety of personnel involved. Additionally, the potential formation of poisonous gases in closed tanks added a layer of complexity. The urgency was intensified by the need to complete the cleaning within a single day, as the water supply for each station depended on these tanks.

Strategic Solutions

 

Addressing these challenges required a comprehensive strategy. Our approach involved assembling an expert team equipped with a systematic cleaning procedure. Tasks such as mud removal, wall cleaning, chemical residue removal, and disinfection were meticulously planned and executed simultaneously. Safety measures, including specialized equipment, machinery, and strict time intervals for workers, were implemented to mitigate potential risks.

Execution and Phased Approach:

 

Recognizing the scale of the project, the cleaning process was initiated in phases, aligning with the metro lines from Line 1 to Line 8. DMRC strategically assigned priority stations and released orders in phases. The adoption of a parallel team approach proved successful, allowing the completion of 12 stations within the stipulated 20-day timeframe during the first phase.

Feedback and Future Phases

​

Post the initial phase, positive feedback from DMRC reinforced the effectiveness of our approach. Future phases will be dictated by the number and significance of stations, as well as the capacities of the tanks. The estimated time for completing the entire project, encompassing several stations, is one year, and the process is ongoing.

Conclusion:

​

This case study underscores the significance of proactive infrastructure maintenance and the successful collaboration between DMRC and our company in addressing critical challenges. The revitalization of firefighting tanks sets a precedent for similar projects, positioning us as a trusted ally in the ongoing endeavor to maintain and improve essential infrastructure.

.

Expansion and Referrals:

 

The success of the tank cleaning project with DMRC has positioned our company as a reliable partner. This success has resulted in referrals to other metro stations in Nagpur, Bangalore, and Chennai, showcasing the trust in our expertise in handling intricate tank cleaning processes.

Conclusion:

 

This case study underscores the significance of proactive infrastructure maintenance and the successful collaboration between DMRC and our company in addressing critical challenges. The revitalization of firefighting tanks sets a precedent for similar projects, positioning us as a trusted ally in the ongoing endeavor to maintain and improve essential infrastructure.

.

bottom of page